Assessment Year | 2016 |
---|---|
Principal Product | Specialty paper products |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
250,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $472,123 | 9,048,865 |
kWh
|
$0.052 |
Electricity Demand | $74,500 | 20,718 |
kW-mo/yr
|
$3.60 |
Electricity Fees | $6,108 | - |
|
- |
Natural Gas | $579,987 | 97,787 |
MMBtu
|
$5.93 |
LPG | $7,700 | 497 |
MMBtu
|
$15.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $150,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $86,449 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $80,322 | $10,300 | - | - |
$80,322
-
MMBtu
|
- | - | - | |
02 | 2.1221: Replace obsolete burners with more efficient ones | $28,176 | $50,000 | - | - |
$28,176
-
MMBtu
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $21,188 | $60,260 |
$18,660
360,225
kWh
|
$2,528
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $4,714 | $1,650 |
$4,211
81,290
kWh
|
$503
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $3,820 | $15,000 |
$(-3,232.0)
(-62,400)
kWh
|
$(-648.0)
-
kW-mo/yr
|
- |
$7,700
-
MMBtu
|
- | - | |
06 | 2.4314: Use synthetic lubricant | $2,870 | $1,000 |
$2,532
48,878
kWh
|
$338
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,273 | $25 |
$2,005
37,800
kWh
|
$268
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7134: Use photocell controls | $2,036 | $6,825 |
$1,755
33,871
kWh
|
$281
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,722 | $1,000 |
$1,519
29,327
kWh
|
$203
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,414 | $2,000 |
$1,247
24,066
kWh
|
$167
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,387 | $414 |
$1,120
21,620
kWh
|
$149
-
kW-mo/yr
|
- | - | $14 | $104 | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $456 | $400 |
$241
4,660
kWh
|
$23
-
kW-mo/yr
|
- | - | $80 | $112 | |
TOTAL RECOMMENDED | $150,378 | $148,874 |
$30,058
579,337
kWh
|
$3,812
-
kW-mo/yr
|
$108,498
-
MMBtu
|
$7,700
-
MMBtu
|
$94 | $216 | ||
TOTAL IMPLEMENTED | $86,449 | $14,114 |
$5,140
99,224
kWh
|
$677
-
kW-mo/yr
|
$80,322
-
MMBtu
|
- | $94 | $216 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs