ITAC Assessment: BD0472
ITAC logo
ITAC Assessment: BD0472
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Overhead door panels
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $5
M
to 10
M
# of Employees 51
Plant Area 126,000
ft2
Annual Production 5,600
pieces
Production Hrs. Annual 4,871
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,551 1,275,255
kWh
Electricity Demand $17,520 3,455
kW-mo/yr
Electricity Fees $2,586 -
Natural Gas $74,450 11,033
MMBtu
LPG $6,187 352
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,698 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,021 $12,366 $5,335
93,757
kWh
$1,171
-
kW-mo/yr
- - $260 $(-745.0)
02 2.1221: Replace obsolete burners with more efficient ones $5,739 $12,000 - - $5,739
-
MMBtu
- - -
03 2.8227: Adjust / maintain fork lift trucks for most efficient operation $5,122 $4,500 $(-1,065.0)
(-18,720)
kWh
- - $6,187
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,121 $300 $919
16,149
kWh
$202
-
kW-mo/yr
- - - -
05 2.4221: Install compressor air intakes in coolest locations $978 $900 $802
14,090
kWh
$176
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $962 $25 $801
14,092
kWh
$161
-
kW-mo/yr
- - - -
07 2.7135: Install occupancy sensors $898 $825 $676
11,873
kWh
$222
-
kW-mo/yr
- - - -
08 2.2437: Recover waste heat from equipment $764 $1,200 - - $764
-
MMBtu
- - -
09 2.4133: Use most efficient type of electric motors $721 $980 $558
9,799
kWh
$163
-
kW-mo/yr
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $197 $75 $162
2,849
kWh
$35
-
kW-mo/yr
- - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $175 $173 $95
1,664
kWh
$12
-
kW-mo/yr
- - $28 $40
TOTAL RECOMMENDED $22,698 $33,344 $8,283
145,553
kWh
$2,142
-
kW-mo/yr
$6,503
-
MMBtu
$6,187
-
MMBtu
$288 $(-705.0)
TOTAL IMPLEMENTED $11,760 $24,366 $5,335
93,757
kWh
$1,171
-
kW-mo/yr
$5,739
-
MMBtu
- $260 $(-745.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs