ITAC Assessment: BD0469
ITAC logo
ITAC Assessment: BD0469
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Overhead Door Panels
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 93,000
ft2
Annual Production 21,600
pieces
Production Hrs. Annual 4,871
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,713 1,283,187
kWh
Electricity Demand $17,639 3,487
kW-mo/yr
Electricity Fees $2,599 -
Natural Gas $72,785 10,972
MMBtu
LPG $4,567 260
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,761

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.8227: Adjust / maintain fork lift trucks for most efficient operation $2,898 $4,090 - - $(-1,738.0)
-
MMBtu
$4,636
-
MMBtu
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,562 $4,770 $2,099
37,009
kWh
$463
-
kW-mo/yr
- - - - -
03 2.7135: Install occupancy sensors $2,198 $750 $1,697
29,934
kWh
$501
-
kW-mo/yr
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $761 $455 $622
10,961
kWh
$139
-
kW-mo/yr
- - - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $681 $20 $558
9,850
kWh
$123
-
kW-mo/yr
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $623 $700 $511
9,014
kWh
$112
-
kW-mo/yr
- - - - -
07 2.2437: Recover waste heat from equipment $591 $1,000 - - $591
-
MMBtu
- - - -
08 2.4133: Use most efficient type of electric motors $290 $1,000 $238
4,197
kWh
$52
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $177 $176 $113
1,997
kWh
$14
-
kW-mo/yr
- - $23 - $27
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $56 $150 $45
802
kWh
$11
-
kW-mo/yr
- - - - -
11 3.5218: Reuse / recycle/ sell rubber products $4,000 $100 - - - - - $4,000 -
TOTAL RECOMMENDED $14,837 $13,211 $5,883
103,764
kWh
$1,415
-
kW-mo/yr
$(-1,147.0)
-
MMBtu
$4,636
-
MMBtu
$23 $4,000 $27
TOTAL IMPLEMENTED $4,761 $555 $622
10,961
kWh
$139
-
kW-mo/yr
- - - $4,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs