Assessment Year | 1999 |
---|---|
Principal Product | Processed fish products |
NAICS |
n/a
|
SIC | 2091: Canned and Cured Fish and Seafoods |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
20,000
ft2
|
Annual Production | 18,000,000
lb
|
Production Hrs. Annual | 3,300
hrs
|
Location (State) | Alaska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $273,231 | 2,449,297 |
kWh
|
$0.11 |
Electricity Demand | $55,076 | 94,416 |
kW-mo/yr
|
$0.58 |
Electricity Fees | $15,393 | - |
|
- |
Fuel Oil #2 | $155,370 | 23,140 |
MMBtu
|
$6.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $702,733 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,049 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $79,500 | $30,000 |
$100,700
1,095,838
kWh
|
$24,600
-
kW-mo/yr
|
- |
$(-35,800.0)
-
MMBtu
|
$(-10,000.0) | - | |
02 | 2.3212: Optimize plant power factor | $6,484 | $6,000 | - | - | $6,484 | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $7,190 | $10,700 |
$5,700
54,807
kWh
|
$1,490
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,400 | $16,800 |
$2,400
23,154
kWh
|
- | - | - | - | - | |
05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $6,070 | - |
$6,070
58,324
kWh
|
- | - | - | - | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,829 | $700 | - | - | - |
$1,829
-
MMBtu
|
- | - | |
07 | 4.445: Install equipment to move product | $519,000 | $250,000 | - | - | - | - | $519,000 | - | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $78,300 | $175,000 |
$700
5,862
kWh
|
- | - | - | $77,600 | - | |
09 | 3.4151: Minimize water usage | $1,960 | - | - | - | - | - | - |
$1,960
-
Tgal
|
|
TOTAL RECOMMENDED | $702,733 | $489,200 |
$115,570
1,237,985
kWh
|
$26,090
-
kW-mo/yr
|
$6,484 |
$(-33,971.0)
-
MMBtu
|
$586,600 |
$1,960
-
Tgal
|
||
TOTAL IMPLEMENTED | $17,049 | $11,400 |
$11,770
113,131
kWh
|
$1,490
-
kW-mo/yr
|
- |
$1,829
-
MMBtu
|
- |
$1,960
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs