ITAC Assessment: ORS001
ITAC logo
ITAC Assessment: ORS001
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Processed fish products
NAICS
n/a
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 20,000
ft2
Annual Production 18,000,000
lb
Production Hrs. Annual 3,300
hrs
Location (State) Alaska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $273,231 2,449,297
kWh
Electricity Demand $55,076 94,416
kW-mo/yr
Electricity Fees $15,393 -
Fuel Oil #2 $155,370 23,140
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $702,733 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,049

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings Water Consumption Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $79,500 $30,000 $100,700
1,095,838
kWh
$24,600
-
kW-mo/yr
- $(-35,800.0)
-
MMBtu
$(-10,000.0) -
02 2.3212: Optimize plant power factor $6,484 $6,000 - - $6,484 - - -
03 2.4133: Use most efficient type of electric motors $7,190 $10,700 $5,700
54,807
kWh
$1,490
-
kW-mo/yr
- - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,400 $16,800 $2,400
23,154
kWh
- - - - -
05 2.2621: Modify refrigeration system to operate at a lower pressure $6,070 - $6,070
58,324
kWh
- - - - -
06 2.1233: Analyze flue gas for proper air/fuel ratio $1,829 $700 - - - $1,829
-
MMBtu
- -
07 4.445: Install equipment to move product $519,000 $250,000 - - - - $519,000 -
08 4.111: Add equipment/ operators to reduce production bottleneck $78,300 $175,000 $700
5,862
kWh
- - - $77,600 -
09 3.4151: Minimize water usage $1,960 - - - - - - $1,960
-
Tgal
TOTAL RECOMMENDED $702,733 $489,200 $115,570
1,237,985
kWh
$26,090
-
kW-mo/yr
$6,484 $(-33,971.0)
-
MMBtu
$586,600 $1,960
-
Tgal
TOTAL IMPLEMENTED $17,049 $11,400 $11,770
113,131
kWh
$1,490
-
kW-mo/yr
- $1,829
-
MMBtu
- $1,960
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs