Assessment Year | 2015 |
---|---|
Principal Product | Overhead door panels |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 38 |
Plant Area |
108,000
ft2
|
Annual Production | 39,425
pieces
|
Production Hrs. Annual | 4,871
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,511 | 1,136,069 |
kWh
|
$0.057 |
Electricity Demand | $15,511 | 3,061 |
kW-mo/yr
|
$5.07 |
Electricity Fees | $2,298 | - |
|
- |
Natural Gas | $63,669 | 9,670 |
MMBtu
|
$6.58 |
LPG | $5,303 | 302 |
MMBtu
|
$17.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,689 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $18,594 | $20 | - | - |
$18,594
-
MMBtu
|
- | - | - | |
02 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $3,531 | $6,000 |
$(-1,772.0)
(-31,200)
kWh
|
- | - |
$5,303
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,204 | $7,793 |
$2,626
46,236
kWh
|
$578
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7134: Use photocell controls | $2,275 | $600 |
$1,678
29,534
kWh
|
$513
-
kW-mo/yr
|
- | - | $14 | $70 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,782 | $600 |
$1,460
25,698
kWh
|
$322
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,202 | $1,500 |
$992
17,456
kWh
|
$210
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $925 | $450 |
$764
13,456
kWh
|
$161
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $707 | $104 |
$580
10,213
kWh
|
$127
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4133: Use most efficient type of electric motors | $660 | $840 |
$535
9,249
kWh
|
$125
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.2136: Install / repair insulation on steam lines | $62 | $110 | - | - |
$62
-
MMBtu
|
- | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $23 | $80 |
$15
262
kWh
|
$8
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $32,965 | $18,097 |
$6,878
120,904
kWh
|
$2,044
-
kW-mo/yr
|
$18,656
-
MMBtu
|
$5,303
-
MMBtu
|
$14 | $70 | ||
TOTAL IMPLEMENTED | $5,689 | $1,754 |
$4,482
78,901
kWh
|
$1,123
-
kW-mo/yr
|
- | - | $14 | $70 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs