ITAC Assessment: BD0461
ITAC logo
ITAC Assessment: BD0461
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Automotive belts
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 275,000
ft2
Annual Production 15,000,000
pieces
Production Hrs. Annual 6,480
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $305,087 5,275,499
kWh
Electricity Demand $26,309 14,861
kW-mo/yr
Electricity Fees $9,197 -
Natural Gas $420,828 70,846
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,669 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,533

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1221: Replace obsolete burners with more efficient ones $38,137 $30,000 - - $38,137
-
MMBtu
- -
02 2.1133: Adjust burners for efficient operation $11,376 $1,000 - - $11,376
-
MMBtu
- -
03 2.1222: Install turbulators $5,742 $1,500 - - $5,742
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,889 $1,000 $3,696
64,622
kWh
$193
-
kW-mo/yr
- - -
05 2.7134: Use photocell controls $2,850 $900 $2,198
38,419
kWh
$234
-
kW-mo/yr
- $261 $157
06 2.2414: Use waste heat from hot flue gases to preheat $2,718 $3,000 $(-968.0)
(-16,917)
kWh
$(-10.6)
-
kW-mo/yr
$3,697
-
MMBtu
- -
07 2.2135: Repair and eliminate steam leaks $1,986 $1,600 - - $1,986
-
MMBtu
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,781 $2,625 $1,685
29,451
kWh
$96
-
kW-mo/yr
- - -
09 2.4221: Install compressor air intakes in coolest locations $1,734 $1,500 $1,648
28,805
kWh
$86
-
kW-mo/yr
- - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,179 $1,665 $1,115
19,500
kWh
$64
-
kW-mo/yr
- - -
11 2.4231: Reduce the pressure of compressed air to the minimum required $874 $20 $831
14,527
kWh
$43
-
kW-mo/yr
- - -
12 2.1123: Install automatic stack damper $871 $1,500 - - $871
-
MMBtu
- -
13 2.2437: Recover waste heat from equipment $1,229 $1,500 - - $1,229
-
MMBtu
- -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $547 $486 $289
5,045
kWh
$12
-
kW-mo/yr
- $104 $142
15 2.7135: Install occupancy sensors $526 $675 $476
8,315
kWh
$50
-
kW-mo/yr
- - -
16 2.3132: Recharge batteries on during off-peak demand periods $230 $20 - $230
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $75,669 $48,991 $10,970
191,767
kWh
$997
-
kW-mo/yr
$63,038
-
MMBtu
$365 $299
TOTAL IMPLEMENTED $23,533 $7,651 $8,699
152,064
kWh
$808
-
kW-mo/yr
$13,362
-
MMBtu
$365 $299
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs