ITAC Assessment: BD0459
ITAC logo
ITAC Assessment: BD0459
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Laminated Paper and Film
NAICS 322220: Paper Bag and Coated and Treated Paper Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 152,800
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,476 1,420,852
kWh
Electricity Demand $29,289 5,561
kW-mo/yr
Electricity Fees $2,398 -
Natural Gas $71,340 9,056
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,020 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,020

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $19,318 $10,000 $13,862
300,681
kWh
$5,456
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $1,792 $1,350 $1,282
27,802
kWh
$510
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $256 $300 $153
3,329
kWh
$24
-
kW-mo/yr
- $36 $43
04 2.7142: Utilize higher efficiency lamps and/or ballasts $392 $1,300 $250
5,432
kWh
$82
-
kW-mo/yr
- $20 $40
05 2.4133: Use most efficient type of electric motors $2,648 $2,700 $2,171
47,083
kWh
$477
-
kW-mo/yr
- - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,004 $300 $823
17,853
kWh
$181
-
kW-mo/yr
- - -
07 2.4226: Use / purchase optimum sized compressor $7,002 $30,399 $6,695
145,238
kWh
$307
-
kW-mo/yr
- - -
08 2.4221: Install compressor air intakes in coolest locations $377 $800 $309
6,703
kWh
$68
-
kW-mo/yr
- - -
09 2.7263: Lower compressor pressure through a/c system modification $142 $20 $116
2,514
kWh
$26
-
kW-mo/yr
- - -
10 2.7231: Use radiant heater for spot heating $1,263 $3,500 - - $1,263
-
MMBtu
- -
11 2.3132: Recharge batteries on during off-peak demand periods $3,826 $18 - $3,826
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $38,020 $50,687 $25,661
556,635
kWh
$10,957
-
kW-mo/yr
$1,263
-
MMBtu
$56 $83
TOTAL IMPLEMENTED $38,020 $50,687 $25,661
556,635
kWh
$10,957
-
kW-mo/yr
$1,263
-
MMBtu
$56 $83
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs