Assessment Year | 2014 |
---|---|
Principal Product | Plastic injection molded parts |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 82 |
Plant Area |
50,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,310 | 1,978,228 |
kWh
|
$0.054 |
Electricity Demand | $22,419 | 4,995 |
kW-mo/yr
|
$4.49 |
Electricity Fees | $2,399 | - |
|
- |
Natural Gas | $4,617 | 577 |
MMBtu
|
$8.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $67,846 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,189 | $1,660 |
$8,239
154,033
kWh
|
$3,950
-
kW-mo/yr
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $6,245 | $825 |
$5,452
101,536
kWh
|
$793
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $283 | $300 |
$159
2,663
kWh
|
$16
-
kW-mo/yr
|
$46 | $62 | - | |
04 | 2.4133: Use most efficient type of electric motors | $10,440 | $17,300 |
$9,518
177,912
kWh
|
$922
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,993 | $590 |
$2,157
40,342
kWh
|
$836
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,193 | $500 |
$457
8,524
kWh
|
$736
-
kW-mo/yr
|
- | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,173 | $20 |
$1,872
34,873
kWh
|
$301
-
kW-mo/yr
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $783 | $100 |
$771
14,365
kWh
|
$12
-
kW-mo/yr
|
- | - | - | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,993 | $875 | - |
$9,993
-
kW-mo/yr
|
- | - | - | |
10 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,470 | $600 | - |
$5,470
-
kW-mo/yr
|
- | - | - | |
11 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,720 | $560 | - |
$2,720
-
kW-mo/yr
|
- | - | - | |
12 | 2.3132: Recharge batteries on during off-peak demand periods | $364 | $20 | - |
$364
-
kW-mo/yr
|
- | - | - | |
13 | 4.322: Eliminate old stock and modify inventory control | $13,000 | $2,000 | - | - | - | - | $13,000 | |
TOTAL RECOMMENDED | $67,846 | $25,350 |
$28,625
534,248
kWh
|
$26,113
-
kW-mo/yr
|
$46 | $62 | $13,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs