Assessment Year | 2014 |
---|---|
Principal Product | Plastic resin pellets |
NAICS | 488991: Packing and Crating |
SIC | 4783: Packing and Crating |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
323,700
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $281,480 | 2,663,579 |
kWh
|
$0.11 |
Natural Gas | $120,525 | 14,142 |
MMBtu
|
$8.52 |
LPG | $59,953 | 2,910 |
MMBtu
|
$20.60 |
Fuel Oil #2 | $325,204 | 13,515 |
MMBtu
|
$24.06 |
Other Gas | $22,891 | 861 |
MMBtu
|
$26.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,471 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $19,966 | $27,000 | - |
$19,966
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,234 | $24,940 |
$15,981
151,204
kWh
|
- | $119 | $134 | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,837 | $1,000 |
$2,837
26,844
kWh
|
- | - | - | |
04 | 2.4321: Upgrade obsolete equipment | $2,486 | $20 |
$2,486
23,522
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,148 | $2,850 |
$2,105
19,918
kWh
|
- | $12 | $31 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,909 | $1,025 |
$1,372
12,982
kWh
|
- | $225 | $312 | |
07 | 2.7134: Use photocell controls | $777 | $450 |
$659
6,234
kWh
|
- | $104 | $14 | |
08 | 2.4133: Use most efficient type of electric motors | $461 | $320 |
$461
4,357
kWh
|
- | - | - | |
09 | 2.7135: Install occupancy sensors | $406 | $750 |
$406
3,840
kWh
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $322 | $143 |
$254
2,402
kWh
|
- | $19 | $49 | |
TOTAL RECOMMENDED | $47,546 | $58,498 |
$26,561
251,303
kWh
|
$19,966
-
MMBtu
|
$479 | $540 | ||
TOTAL IMPLEMENTED | $7,471 | $3,870 |
$7,428
70,284
kWh
|
- | $12 | $31 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs