Assessment Year | 2014 |
---|---|
Principal Product | Plastic Film |
NAICS | 326111: Plastics Bag and Pouch Manufacturing |
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
69,500
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,609 | 1,520,460 |
kWh
|
$0.058 |
Electricity Demand | $63,618 | 3,669 |
kW-mo/yr
|
$17.34 |
Electricity Fees | $1,220 | - |
|
- |
Natural Gas | $37,436 | 5,972 |
MMBtu
|
$6.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $111,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $81,339 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2692: Use outside cold water source as a supply of cooling water | $64,237 | $1,500,000 |
$39,926
692,711
kWh
|
$24,311
-
kW-mo/yr
|
- | - | - | |
02 | 2.7231: Use radiant heater for spot heating | $13,551 | $16,500 |
$1,508
26,185
kWh
|
$3,676
-
kW-mo/yr
|
$8,367
-
MMBtu
|
- | - | |
03 | 2.7134: Use photocell controls | $12,784 | $7,575 |
$4,313
74,873
kWh
|
$7,883
-
kW-mo/yr
|
- | $504 | $84 | |
04 | 2.7122: Disconnect ballasts | $9,963 | $725 |
$6,191
107,490
kWh
|
$3,772
-
kW-mo/yr
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $3,233 | $750 |
$1,457
25,303
kWh
|
$1,776
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,491 | $20 |
$1,548
26,882
kWh
|
$943
-
kW-mo/yr
|
- | - | - | |
07 | 2.3132: Recharge batteries on during off-peak demand periods | $2,288 | $40 | - |
$2,288
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,827 | $2,800 |
$1,119
19,429
kWh
|
$682
-
kW-mo/yr
|
- | $9 | $17 | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $739 | $600 |
$355
6,165
kWh
|
$204
-
kW-mo/yr
|
- | $72 | $108 | |
10 | 2.4221: Install compressor air intakes in coolest locations | $407 | $700 |
$253
4,392
kWh
|
$154
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $111,520 | $1,529,710 |
$56,670
983,430
kWh
|
$45,689
-
kW-mo/yr
|
$8,367
-
MMBtu
|
$585 | $209 | ||
TOTAL IMPLEMENTED | $81,339 | $1,510,395 |
$46,906
813,895
kWh
|
$33,819
-
kW-mo/yr
|
- | $513 | $101 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs