ITAC Assessment: BD0448
ITAC logo
ITAC Assessment: BD0448
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Food ingredients, ready-to-eat cereal
NAICS 311230: Breakfast Cereal Manufacturing
SIC 2043: Cereal Breakfast Foods
Sales Range $50
M
to 100
M
# of Employees 177
Plant Area 150,000
ft2
Annual Production 60,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $687,049 12,373,659
kWh
Electricity Demand $149,117 27,740
kW-mo/yr
Electricity Fees $13,840 -
Natural Gas $430,167 115,334
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $216,064 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $149,002

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1116: Improve combustion control capability $51,953 $95,000 - - $51,953
-
MMBtu
- - -
02 2.1222: Install turbulators $18,699 $5,000 - - $18,699
-
MMBtu
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $14,582 $17,750 $12,075
217,560
kWh
$1,603
-
kW-mo/yr
- - $696 $208
04 2.1233: Analyze flue gas for proper air/fuel ratio $14,011 $10,000 - - $14,011
-
MMBtu
- - -
05 2.4133: Use most efficient type of electric motors $13,680 $9,880 $12,076
217,591
kWh
$1,604
-
kW-mo/yr
- - - -
06 2.1221: Replace obsolete burners with more efficient ones $13,135 $30,000 - - $13,135
-
MMBtu
- - -
07 2.7135: Install occupancy sensors $3,869 $1,625 $2,999
54,032
kWh
$870
-
kW-mo/yr
- - - -
08 2.2414: Use waste heat from hot flue gases to preheat $3,695 $3,000 $(-648.0)
(-11,680)
kWh
$(-65.0)
-
kW-mo/yr
$4,408
-
MMBtu
- - -
09 2.4221: Install compressor air intakes in coolest locations $2,990 $1,000 $2,640
47,569
kWh
$350
-
kW-mo/yr
- - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $2,621 $120 $2,314
41,693
kWh
$307
-
kW-mo/yr
- - - -
11 2.3132: Recharge batteries on during off-peak demand periods $2,517 $45 - $2,517
-
kW-mo/yr
- - - -
12 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,070 $40 - $1,070
-
kW-mo/yr
- - - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $668 $600 $406
7,323
kWh
$54
-
kW-mo/yr
- - $86 $122
14 3.4114: Replace city water with recycled water via cooling tower $61,924 $25,000 $(-2,613.0)
(-47,073)
kWh
$(-305.0)
-
kW-mo/yr
- $65,842
-
Tgal
$(-1,000.0) -
15 4.652: Replace existing equipment with more suitable substitutes $10,650 $30,000 - - - - $10,650 -
TOTAL RECOMMENDED $216,064 $229,060 $29,249
527,015
kWh
$8,005
-
kW-mo/yr
$102,206
-
MMBtu
$65,842
-
Tgal
$10,432 $330
TOTAL IMPLEMENTED $149,002 $203,895 $29,548
532,395
kWh
$5,486
-
kW-mo/yr
$102,206
-
MMBtu
- $11,432 $330
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs