ITAC Assessment: BD0440
ITAC logo
ITAC Assessment: BD0440
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Canned pumpkin and pie mix
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $100
M
to 500
M
# of Employees 180
Plant Area 180,000
ft2
Annual Production 100,000,000
lb
Production Hrs. Annual 2,016
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,526 2,474,300
kWh
Electricity Demand $24,349 6,081
kW-mo/yr
Electricity Fees $9,109 -
Natural Gas $441,500 77,179
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $139,546 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2121: Increase amount of condensate returned $54,036 $150,000 - - $41,110
-
MMBtu
- $12,926
02 2.1224: Replace boiler $35,950 $170,000 - - $35,950
-
MMBtu
- -
03 2.7231: Use radiant heater for spot heating $17,194 $15,200 - - $17,194
-
MMBtu
- -
04 2.2136: Install / repair insulation on steam lines $6,523 $6,400 - - $6,523
-
MMBtu
- -
05 2.4133: Use most efficient type of electric motors $6,300 $22,220 $4,135
121,258
kWh
$2,165
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,816 $3,025 $1,249
36,617
kWh
$201
-
kW-mo/yr
- $552 $815
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,177 $20 $1,110
32,541
kWh
$67
-
kW-mo/yr
- - -
08 2.4221: Install compressor air intakes in coolest locations $1,947 $4,500 $1,811
53,116
kWh
$136
-
kW-mo/yr
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,645 $4,750 $783
22,939
kWh
$862
-
kW-mo/yr
- - -
10 2.3132: Recharge batteries on during off-peak demand periods $570 $40 - $570
-
kW-mo/yr
- - -
11 3.5315: Lease / purchase baler; sell cardboard to recycler $11,389 $8,000 - - - - $11,389
TOTAL RECOMMENDED $139,546 $384,155 $9,088
266,471
kWh
$4,000
-
kW-mo/yr
$100,777
-
MMBtu
$552 $25,130
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs