ITAC Assessment: BD0437
ITAC logo
ITAC Assessment: BD0437
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Metal finishing, sorting, and coating
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 160,000
ft2
Annual Production 60,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $249,199 4,602,704
kWh
Electricity Demand $43,463 7,717
kW-mo/yr
Electricity Fees $2,144 -
Natural Gas $326,314 63,877
MMBtu
Fuel Oil #2 $205,920 7,280
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $339,958 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.8226: Increase efficiency of trucks $168,734 $780,000 - - $(-37,186.0)
-
MMBtu
$205,920
-
MMBtu
02 2.7231: Use radiant heater for spot heating $87,468 $54,000 - - $87,468
-
MMBtu
-
03 2.1221: Replace obsolete burners with more efficient ones $33,735 $100,000 - - $33,735
-
MMBtu
-
04 2.1213: Direct warmest air to combustion intake $19,574 $15,000 $(-315.0)
(-5,824)
kWh
$(-68.0)
-
kW-mo/yr
$19,957
-
MMBtu
-
05 2.1221: Replace obsolete burners with more efficient ones $7,315 $20,000 - - $7,315
-
MMBtu
-
06 2.4133: Use most efficient type of electric motors $6,643 $10,000 $5,893
108,927
kWh
$750
-
kW-mo/yr
- -
07 2.4221: Install compressor air intakes in coolest locations $5,609 $1,000 $4,910
90,764
kWh
$699
-
kW-mo/yr
- -
08 2.1222: Install turbulators $5,570 $2,600 - - $5,570
-
MMBtu
-
09 2.4231: Reduce the pressure of compressed air to the minimum required $4,532 $20 $3,967
73,330
kWh
$565
-
kW-mo/yr
- -
10 2.7135: Install occupancy sensors $510 $1,875 $268
4,960
kWh
$242
-
kW-mo/yr
- -
11 2.3137: Use power during off-peak periods $268 $60 - $268
-
kW-mo/yr
- -
TOTAL RECOMMENDED $339,958 $984,555 $14,723
272,157
kWh
$2,456
-
kW-mo/yr
$116,859
-
MMBtu
$205,920
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs