Assessment Year | 2013 |
---|---|
Principal Product | Fabricated light steel products |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $1 M to 5M |
# of Employees | 19 |
Plant Area |
35,440
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 1,768
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,595 | 558,701 |
kWh
|
$0.064 |
Electricity Demand | $10,161 | 3,126 |
kW-mo/yr
|
$3.25 |
Electricity Fees | $2,766 | - |
|
- |
Natural Gas | $15,000 | 2,241 |
MMBtu
|
$6.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,656 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,500 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $7,450 | $22,500 | - | - |
$7,450
-
MMBtu
|
- | - | - | |
02 | 2.7134: Use photocell controls | $2,289 | $200 |
$343
5,381
kWh
|
$288
-
kW-mo/yr
|
- | $1,624 | $34 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,001 | $3,520 |
$718
11,267
kWh
|
$249
-
kW-mo/yr
|
- | - | $34 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $741 | $25 |
$570
8,995
kWh
|
$171
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $397 | $200 |
$397
6,232
kWh
|
- | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $278 | $600 |
$207
3,247
kWh
|
$71
-
kW-mo/yr
|
- | - | - | - | |
07 | 4.322: Eliminate old stock and modify inventory control | $4,500 | $10,000 | - | - | - | - | - | $4,500 | |
TOTAL RECOMMENDED | $16,656 | $37,045 |
$2,235
35,122
kWh
|
$779
-
kW-mo/yr
|
$7,450
-
MMBtu
|
$1,624 | $68 | $4,500 | ||
TOTAL IMPLEMENTED | $4,500 | $10,000 | - | - | - | - | - | $4,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs