ITAC Assessment: BD0430
ITAC logo
ITAC Assessment: BD0430
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Fabricated light steel products
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $1
M
to 5
M
# of Employees 19
Plant Area 35,440
ft2
Annual Production 1
units
Production Hrs. Annual 1,768
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,595 558,701
kWh
Electricity Demand $10,161 3,126
kW-mo/yr
Electricity Fees $2,766 -
Natural Gas $15,000 2,241
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,656 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7231: Use radiant heater for spot heating $7,450 $22,500 - - $7,450
-
MMBtu
- - -
02 2.7134: Use photocell controls $2,289 $200 $343
5,381
kWh
$288
-
kW-mo/yr
- $1,624 $34 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,001 $3,520 $718
11,267
kWh
$249
-
kW-mo/yr
- - $34 -
04 2.4231: Reduce the pressure of compressed air to the minimum required $741 $25 $570
8,995
kWh
$171
-
kW-mo/yr
- - - -
05 2.7135: Install occupancy sensors $397 $200 $397
6,232
kWh
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $278 $600 $207
3,247
kWh
$71
-
kW-mo/yr
- - - -
07 4.322: Eliminate old stock and modify inventory control $4,500 $10,000 - - - - - $4,500
TOTAL RECOMMENDED $16,656 $37,045 $2,235
35,122
kWh
$779
-
kW-mo/yr
$7,450
-
MMBtu
$1,624 $68 $4,500
TOTAL IMPLEMENTED $4,500 $10,000 - - - - - $4,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs