Assessment Year | 2012 |
---|---|
Principal Product | Plastic Trash Bags |
NAICS | 326111: Plastics Bag and Pouch Manufacturing |
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
66,900
ft2
|
Annual Production | 55,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $789,931 | 11,056,039 |
kWh
|
$0.071 |
Electricity Demand | $117,225 | 20,987 |
kW-mo/yr
|
$5.59 |
Electricity Fees | $12,531 | - |
|
- |
Natural Gas | $3,025 | 265 |
MMBtu
|
$11.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $103,305 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,204 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $68,497 | $102,400 |
$61,862
866,409
kWh
|
$6,635
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,674 | $20 |
$9,640
135,020
kWh
|
$1,034
-
kW-mo/yr
|
- | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $8,975 | $1,200 |
$8,106
113,530
kWh
|
$869
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $7,526 | $1,500 |
$6,804
95,289
kWh
|
$722
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,204 | $4,750 |
$4,665
65,336
kWh
|
$539
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,989 | $1,530 |
$1,696
23,750
kWh
|
$293
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $440 | $197 |
$214
2,995
kWh
|
$23
-
kW-mo/yr
|
$94 | $109 | |
TOTAL RECOMMENDED | $103,305 | $111,597 |
$92,987
1,302,329
kWh
|
$10,115
-
kW-mo/yr
|
$94 | $109 | ||
TOTAL IMPLEMENTED | $5,204 | $4,750 |
$4,665
65,336
kWh
|
$539
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs