Assessment Year | 2012 |
---|---|
Principal Product | Centrifugal pumps |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
80,000
ft2
|
Annual Production | 1,200
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,509 | 2,086,280 |
kWh
|
$0.049 |
Electricity Demand | $66,144 | 9,022 |
kW-mo/yr
|
$7.33 |
Electricity Fees | $99 | - |
|
- |
Natural Gas | $21,445 | 2,280 |
MMBtu
|
$9.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,652 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,369 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,259 | $41,728 |
$11,853
241,428
kWh
|
$3,406
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $11,228 | $2,550 |
$9,350
190,437
kWh
|
$1,878
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $4,270 | $2,500 |
$(-154.0)
(-3,120)
kWh
|
$(-48.0)
-
kW-mo/yr
|
$4,472
-
MMBtu
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,040 | $3,510 |
$1,426
29,070
kWh
|
$614
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,253 | $10 |
$2,505
51,026
kWh
|
$748
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $793 | $500 |
$610
12,431
kWh
|
$183
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $535 | $450 |
$262
5,326
kWh
|
$53
-
kW-mo/yr
|
- | - | - | $92 | $128 | |
08 | 2.7134: Use photocell controls | $307 | $200 |
$200
4,082
kWh
|
$107
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 3.4111: Use closed cycle process to minimize waste water production | $1,782 | $1,500 | - | - | - |
$1,782
-
Tgal
|
- | - | - | |
10 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $1,032 | $1,600 | - | - | - | - | - | - | $1,032 | |
11 | 3.3131: Use evaporation to concentrate material | $153 | $600 |
$(-285.0)
(-5,797)
kWh
|
- | - | - |
$1,188
-
gal
|
$(-750.0) | - | |
TOTAL RECOMMENDED | $40,652 | $55,148 |
$25,767
524,883
kWh
|
$6,941
-
kW-mo/yr
|
$4,472
-
MMBtu
|
$1,782
-
Tgal
|
$1,188
-
gal
|
$(-658.0) | $1,160 | ||
TOTAL IMPLEMENTED | $29,369 | $48,438 |
$23,091
470,343
kWh
|
$6,058
-
kW-mo/yr
|
- | - | - | $92 | $128 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs