Assessment Year | 2012 |
---|---|
Principal Product | Fuel and hydraulic spin-on filters |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 103 |
Plant Area |
61,500
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 2,704
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,113 | 1,646,525 |
kWh
|
$0.066 |
Electricity Demand | $36,344 | 6,999 |
kW-mo/yr
|
$5.19 |
Electricity Fees | $8,966 | - |
|
- |
Natural Gas | $54,938 | 7,550 |
MMBtu
|
$7.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,001 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,688 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $23,702 | $57,000 |
$27,366
416,520
kWh
|
$9,977
-
kW-mo/yr
|
$(-13,641.0)
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $15,937 | $1,500 |
$11,679
177,764
kWh
|
$4,258
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,611 | $50 |
$3,445
52,433
kWh
|
$1,166
-
kW-mo/yr
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $1,622 | $4,000 | - | - |
$1,622
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $154 | $20 |
$124
1,331
kWh
|
$30
-
kW-mo/yr
|
- | - | |
06 | 3.5311: Recover and reuse waste material | $975 | $400 | - | - | - | $975 | |
TOTAL RECOMMENDED | $47,001 | $62,970 |
$42,614
648,048
kWh
|
$15,431
-
kW-mo/yr
|
$(-12,019.0)
-
MMBtu
|
$975 | ||
TOTAL IMPLEMENTED | $18,688 | $5,920 |
$11,803
179,095
kWh
|
$4,288
-
kW-mo/yr
|
$1,622
-
MMBtu
|
$975 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs