Assessment Year | 2002 |
---|---|
Principal Product | Aseptic Packaging |
NAICS |
n/a
|
SIC | 2898: |
Sales Range | $100 M to 500M |
# of Employees | 160 |
Plant Area |
90,000
ft2
|
Annual Production | 2,000,000,000
pieces
|
Production Hrs. Annual | 6,264
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,035,206 | 20,244,000 |
kWh
|
$0.051 |
Electricity Demand | $433,989 | 47,745 |
kW-mo/yr
|
$9.09 |
Natural Gas | $59,581 | 14,295 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $88,130 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $49,940 | - |
$49,940
972,274
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,330 | - |
$8,310
161,800
kWh
|
$2,020
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $6,515 | - |
$6,515
126,840
kWh
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $5,770 | - |
$4,290
83,512
kWh
|
$1,480
-
kW-mo/yr
|
- | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,290 | - |
$6,290
122,460
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $4,580 | - | - | - | $4,580 | |
07 | 2.6218: Turn off equipment when not in use | $3,840 | - |
$3,840
74,790
kWh
|
- | - | |
08 | 2.7124: Make a practice of turning off lights when not needed | $2,805 | - |
$1,675
37,645
kWh
|
$1,130
-
kW-mo/yr
|
- | |
09 | 2.7135: Install occupancy sensors | $2,640 | - |
$2,640
51,640
kWh
|
- | - | |
TOTAL RECOMMENDED | $92,710 | - |
$83,500
1,630,961
kWh
|
$4,630
-
kW-mo/yr
|
$4,580 | ||
TOTAL IMPLEMENTED | $88,130 | - |
$83,500
1,630,961
kWh
|
$4,630
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs