ITAC Assessment: BD0395
ITAC logo
ITAC Assessment: BD0395
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Wire-mesh cable trays
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 76,120
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 4,380
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,531 1,062,000
kWh
Electricity Demand $24,062 3,000
kW-mo/yr
Electricity Fees $6,858 -
Natural Gas $6,272 766
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,625 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,701

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,465 $34,827 $14,465
171,586
kWh
- -
02 2.4133: Use most efficient type of electric motors $1,656 $2,150 $1,124
13,328
kWh
$532
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $1,621 $825 $989
11,734
kWh
$632
-
kW-mo/yr
-
04 2.7231: Use radiant heater for spot heating $1,380 $1,500 - - $1,380
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $888 $1,000 $785
9,312
kWh
$103
-
kW-mo/yr
-
06 2.7134: Use photocell controls $615 $375 $277
3,285
kWh
$338
-
kW-mo/yr
-
TOTAL RECOMMENDED $20,625 $40,677 $17,640
209,245
kWh
$1,605
-
kW-mo/yr
$1,380
-
MMBtu
TOTAL IMPLEMENTED $16,701 $36,027 $15,731
186,605
kWh
$970
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs