Assessment Year | 2011 |
---|---|
Principal Product | Automotive Seating |
NAICS | 336360: Motor Vehicle Seating and Interior Trim Manufacturing |
SIC | 2531: Public Building and Related Furniture |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
97,185
ft2
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,694 | 798,369 |
kWh
|
$0.076 |
Electricity Demand | $7,494 | 3,074 |
kW-mo/yr
|
$2.44 |
Electricity Fees | $11,494 | - |
|
- |
Natural Gas | $17,425 | 2,890 |
MMBtu
|
$6.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,347 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,012 | $21,240 |
$6,760
88,947
kWh
|
$1,252
-
kW-mo/yr
|
- | - | - | |
02 | 2.1222: Install turbulators | $2,436 | $2,500 | - | - |
$2,436
-
MMBtu
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $1,595 | $4,000 |
$(-122.0)
(-1,600)
kWh
|
- |
$1,717
-
MMBtu
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $453 | $300 |
$382
5,028
kWh
|
$71
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $272 | $500 |
$248
3,267
kWh
|
$24
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $434 | $237 |
$304
3,995
kWh
|
$13
-
kW-mo/yr
|
- | $57 | $60 | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $145 | $510 |
$118
1,560
kWh
|
$27
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $13,347 | $29,287 |
$7,690
101,197
kWh
|
$1,387
-
kW-mo/yr
|
$4,153
-
MMBtu
|
$57 | $60 | ||
TOTAL IMPLEMENTED | $12,749 | $28,477 |
$7,190
94,609
kWh
|
$1,289
-
kW-mo/yr
|
$4,153
-
MMBtu
|
$57 | $60 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs