ITAC Assessment: BD0388
ITAC logo
ITAC Assessment: BD0388
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Wheels, Bearings, Ball Transfers
NAICS 333613: Mechanical Power Transmission Equipment Manufacturing
SIC 3535: Conveyors and Conveying Equipment
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 80,000
ft2
Annual Production 12,729,895
pieces
Production Hrs. Annual 3,120
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $203,746 3,185,348
kWh
Electricity Demand $54,231 8,931
kW-mo/yr
Electricity Fees $11,515 -
Natural Gas $135,435 25,697
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $111,113 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.2314: Replace heat treating oven with more efficient unit $12,465 $60,000 - - $12,465
-
MMBtu
-
02 2.7231: Use radiant heater for spot heating $30,750 $20,000 - - $30,750
-
MMBtu
-
03 2.1113: Reduce combustion air flow to optimum $2,470 $4,000 $(-210.0)
(-3,340)
kWh
- $2,680
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $1,581 $1,200 $1,560
18,449
kWh
$21
-
kW-mo/yr
- -
05 3.3125: Use distillation, evaporation to remove contaminants $63,847 $26,000 - - - $63,847
-
gal
TOTAL RECOMMENDED $111,113 $111,200 $1,350
15,109
kWh
$21
-
kW-mo/yr
$45,895
-
MMBtu
$63,847
-
gal
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs