| Assessment Year | 2011 |
|---|---|
| Principal Product | Sewer cleaners |
| NAICS | 336211: Motor Vehicle Body Manufacturing |
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $100 M to 500M |
| # of Employees | 427 |
| Plant Area |
250,000
ft2
|
| Annual Production | 606
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $206,150 | 4,741,888 |
kWh
|
$0.043 |
| Electricity Demand | $67,828 | 11,869 |
kW-mo/yr
|
$5.71 |
| Electricity Fees | $115,727 | - |
|
- |
| Natural Gas | $292,103 | 44,348 |
MMBtu
|
$6.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $111,857 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $89,054 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $50,720 | $73,600 | - | - |
$50,720
-
MMBtu
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,663 | $45,984 |
$24,198
574,779
kWh
|
$8,465
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.1221: Replace obsolete burners with more efficient ones | $13,232 | $3,000 | - | - |
$13,232
-
MMBtu
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,079 | $1,400 |
$5,944
141,180
kWh
|
$1,550
-
kW-mo/yr
|
- | - | $52 | - | $533 | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $2,049 | $5,100 |
$1,473
34,977
kWh
|
$576
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,941 | $2,000 |
$1,538
36,544
kWh
|
$403
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.7135: Install occupancy sensors | $1,067 | $1,067 |
$590
14,019
kWh
|
$477
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $614 | $525 |
$266
6,325
kWh
|
$49
-
kW-mo/yr
|
- | - | $147 | - | $152 | |
| 09 | 3.3131: Use evaporation to concentrate material | $949 | $705 |
$(-26.0)
(-399)
kWh
|
- | - |
$1,975
-
gal
|
- | $(-1,000.0) | - | |
| 10 | 4.454: Modify startup/shutdown times | $543 | $20 | - |
$543
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $111,857 | $133,401 |
$33,983
807,425
kWh
|
$12,063
-
kW-mo/yr
|
$63,952
-
MMBtu
|
$1,975
-
gal
|
$199 | $(-1,000.0) | $685 | ||
| TOTAL IMPLEMENTED | $89,054 | $128,276 |
$28,065
666,644
kWh
|
$9,970
-
kW-mo/yr
|
$50,720
-
MMBtu
|
- | $147 | - | $152 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs