ITAC Assessment: BD0383
ITAC logo
ITAC Assessment: BD0383
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Printed paper products
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 75,848
ft2
Annual Production 350,357,004
pieces
Production Hrs. Annual 8,112
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $237,850 3,925,380
kWh
Electricity Demand $51,164 9,593
kW-mo/yr
Electricity Fees $33,412 -
Natural Gas $26,959 2,929
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $56,646 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $22,085 $7,000 - - $22,085
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $21,355 $7,633 $18,986
309,700
kWh
$2,369
-
kW-mo/yr
-
03 2.7231: Use radiant heater for spot heating $8,456 $4,240 - - $8,456
-
MMBtu
04 2.4133: Use most efficient type of electric motors $2,708 $1,620 $2,428
40,062
kWh
$280
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $1,087 $1,500 $966
15,942
kWh
$121
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $955 $975 $832
13,733
kWh
$123
-
kW-mo/yr
-
TOTAL RECOMMENDED $56,646 $22,968 $23,212
379,437
kWh
$2,893
-
kW-mo/yr
$30,541
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs