Assessment Year | 2010 |
---|---|
Principal Product | Fixtures and displays |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $10 M to 50M |
# of Employees | 134 |
Plant Area |
312,000
ft2
|
Annual Production | 287,000
pieces
|
Production Hrs. Annual | 6,175
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $190,854 | 2,726,479 |
kWh
|
$0.070 |
Electricity Demand | $43,924 | 18,565 |
kW-mo/yr
|
$2.37 |
Electricity Fees | $25,302 | - |
|
- |
Natural Gas | $100,108 | 15,211 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,091 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,928 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $15,800 | $18,200 |
$12,293
155,610
kWh
|
$3,507
-
kW-mo/yr
|
- | - | |
02 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $6,928 | $11 | - | - |
$6,928
-
MMBtu
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $2,388 | $3,780 |
$2,261
28,482
kWh
|
$127
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,681 | $420 |
$1,564
19,694
kWh
|
$117
-
kW-mo/yr
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $1,119 | $1,500 | - | - |
$1,119
-
MMBtu
|
- | |
06 | 2.4314: Use synthetic lubricant | $873 | $600 |
$812
10,226
kWh
|
$61
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $748 | $21 |
$696
8,772
kWh
|
$52
-
kW-mo/yr
|
- | - | |
08 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $1,554 | $2,750 | - | - | - |
$1,554
-
gal
|
|
TOTAL RECOMMENDED | $31,091 | $27,282 |
$17,626
222,784
kWh
|
$3,864
-
kW-mo/yr
|
$8,047
-
MMBtu
|
$1,554
-
gal
|
||
TOTAL IMPLEMENTED | $6,928 | $11 | - | - |
$6,928
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs