Assessment Year | 2010 |
---|---|
Principal Product | Baked goods |
NAICS | 311919: Other Snack Food Manufacturing |
SIC | 2052: Cookies and Crackers |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
187,484
ft2
|
Annual Production | 55,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $422,973 | 5,666,443 |
kWh
|
$0.075 |
Electricity Demand | $71,311 | 12,991 |
kW-mo/yr
|
$5.49 |
Electricity Fees | $29,159 | - |
|
- |
Natural Gas | $273,177 | 33,310 |
MMBtu
|
$8.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,140 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,406 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $9,620 | $210 |
$9,620
129,651
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,837 | $2,700 |
$10,362
139,651
kWh
|
$1,475
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,342 | $1,000 |
$2,074
27,958
kWh
|
$268
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,922 | - |
$5,243
70,662
kWh
|
$679
-
kW-mo/yr
|
- | |
05 | 2.4312: Improve lubrication practices | $2,368 | $600 |
$2,097
28,266
kWh
|
$271
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $3,606 | $3,000 | - | - |
$3,606
-
MMBtu
|
|
07 | 2.2442: Preheat combustion air with waste heat | $21,299 | $18,000 |
$(-6,839.0)
(-92,170)
kWh
|
$(-884.0)
-
kW-mo/yr
|
$29,022
-
MMBtu
|
|
08 | 2.4133: Use most efficient type of electric motors | $4,581 | $6,400 |
$4,176
56,284
kWh
|
$405
-
kW-mo/yr
|
- | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $565 | - | - |
$565
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $62,140 | $31,910 |
$26,733
360,302
kWh
|
$2,779
-
kW-mo/yr
|
$32,628
-
MMBtu
|
||
TOTAL IMPLEMENTED | $28,406 | $9,910 |
$26,255
353,852
kWh
|
$2,151
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs