Assessment Year | 2009 |
---|---|
Principal Product | Motorcyle and Automotive Part |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
40,000
ft2
|
Annual Production | 576,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $230,075 | 3,243,267 |
kWh
|
$0.071 |
Electricity Demand | $66,249 | 7,497 |
kW-mo/yr
|
$8.84 |
Electricity Fees | $7,748 | - |
|
- |
Natural Gas | $309,080 | 31,310 |
MMBtu
|
$9.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $254,336 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,534 | $5,810 |
$9,778
184,493
kWh
|
$2,421
-
kW-mo/yr
|
- | - | $313 | - | $22 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,135 | $19,446 |
$5,588
105,440
kWh
|
$1,547
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7135: Install occupancy sensors | $6,817 | $3,450 |
$3,791
71,533
kWh
|
$3,026
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $284 | $250 |
$141
2,663
kWh
|
$33
-
kW-mo/yr
|
- | - | $46 | - | $64 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $424 | $500 |
$340
6,419
kWh
|
- | $84 | - | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,907 | - |
$1,529
28,851
kWh
|
$378
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,480 | $300 |
$15,102
284,948
kWh
|
$378
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $17,476 | $21,600 |
$11,426
215,579
kWh
|
$6,050
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.2511: Insulate bare equipment | $1,229 | $392 |
$1,229
23,184
kWh
|
- | - | - | - | - | - | |
10 | 2.1116: Improve combustion control capability | $33,921 | $3,500 | - | - | - |
$33,921
-
MMBtu
|
- | - | - | |
11 | 2.1221: Replace obsolete burners with more efficient ones | $74,498 | $10,000 | - | - | - |
$74,498
-
MMBtu
|
- | - | - | |
12 | 2.1222: Install turbulators | $49,164 | $2,500 | - | - | - |
$49,164
-
MMBtu
|
- | - | - | |
13 | 2.7231: Use radiant heater for spot heating | $23,508 | $5,200 |
$9,880
186,425
kWh
|
$2,812
-
kW-mo/yr
|
- |
$10,816
-
MMBtu
|
- | - | - | |
14 | 4.821: Pay bills on time to avoid late fees | $9,959 | - | - | - | - | - | - | $9,959 | - | |
TOTAL RECOMMENDED | $254,336 | $72,948 |
$58,804
1,109,535
kWh
|
$16,645
-
kW-mo/yr
|
$84 |
$168,399
-
MMBtu
|
$359 | $9,959 | $86 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs