Assessment Year | 2009 |
---|---|
Principal Product | Die Cut Lidding |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $50 M to 100M |
# of Employees | 122 |
Plant Area |
86,000
ft2
|
Annual Production | 4,000,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $278,710 | 3,925,008 |
kWh
|
$0.071 |
Electricity Demand | $44,591 | 20,955 |
kW-mo/yr
|
$2.13 |
Electricity Fees | $14,663 | - |
|
- |
Natural Gas | $199,101 | 16,847 |
MMBtu
|
$11.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $458,177 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $359,522 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $4,893 | $241 |
$3,871
51,868
kWh
|
$208
-
kW-mo/yr
|
- | $513 | $301 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $565 | $491 |
$375
5,326
kWh
|
$16
-
kW-mo/yr
|
- | $80 | $94 | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $10,495 | $3,961 |
$8,359
118,565
kWh
|
$1,108
-
kW-mo/yr
|
- | $514 | $514 | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,911 | $2 |
$1,802
25,563
kWh
|
$109
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $24,734 | $501 | - | - |
$24,734
-
MMBtu
|
- | - | |
06 | 2.1224: Replace boiler | $9,256 | $601 | - | - |
$9,256
-
MMBtu
|
- | - | |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $34,960 | $24,000 | - | - |
$6,772
-
MMBtu
|
$28,188 | - | |
08 | 2.7231: Use radiant heater for spot heating | $32,157 | $5,301 | - | - |
$32,157
-
MMBtu
|
- | - | |
09 | 4.441: Install automatic packing equipment | $339,206 | $5,001 | - | - | - | $339,206 | - | |
TOTAL RECOMMENDED | $458,177 | $40,099 |
$14,407
201,322
kWh
|
$1,441
-
kW-mo/yr
|
$72,919
-
MMBtu
|
$368,501 | $909 | ||
TOTAL IMPLEMENTED | $359,522 | $10,054 |
$8,734
123,891
kWh
|
$1,124
-
kW-mo/yr
|
$9,256
-
MMBtu
|
$339,800 | $608 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs