| Assessment Year | 2008 |
|---|---|
| Principal Product | custom-machined metals |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 260 |
| Plant Area |
230,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,264
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $411,063 | 8,378,234 |
kWh
|
$0.049 |
| Electricity Demand | $63,372 | 6,967 |
kW-mo/yr
|
$9.10 |
| Electricity Fees | $78,808 | - |
|
- |
| Natural Gas | $31,784 | 3,536 |
MMBtu
|
$8.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $120,385 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,434 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $51,977 | $120 |
$38,206
778,151
kWh
|
$13,771
-
kW-mo/yr
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $4,457 | $5,400 |
$2,871
58,465
kWh
|
$1,586
-
kW-mo/yr
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,032 | $2 |
$4,013
81,733
kWh
|
$1,019
-
kW-mo/yr
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $9,195 | $501 |
$7,333
149,348
kWh
|
$1,862
-
kW-mo/yr
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $41,601 | $43,021 |
$41,600
732,387
kWh
|
$1
-
kW-mo/yr
|
- | - | |
| 06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $898 | $2,101 | - | - | - |
$898
-
lb
|
|
| 07 | 3.5316: Contract a wood pallet recycling company | $1,228 | $257 | - | - | - |
$1,228
-
lb
|
|
| 08 | 3.3131: Use evaporation to concentrate material | $5,997 | $7,996 | - | - |
$5,997
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $120,385 | $59,398 |
$94,023
1,800,084
kWh
|
$18,239
-
kW-mo/yr
|
$5,997
-
Tgal
|
$2,126
-
lb
|
||
| TOTAL IMPLEMENTED | $56,434 | $5,520 |
$41,077
836,616
kWh
|
$15,357
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs