Assessment Year | 2008 |
---|---|
Principal Product | Sketchboards,Arthorse,Linoblocks,Pallets |
NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 13 |
Plant Area |
24,000
ft2
|
Annual Production | 61,712
lb
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,623 | 270,264 |
kWh
|
$0.10 |
Natural Gas | $12,783 | 1,267 |
MMBtu
|
$10.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,387 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,896 | $6,840 |
$2,896
111
kWh
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $413 | $725 |
$413
16
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $324 | $550 |
$131
5
kWh
|
- | $81 | $112 | |
04 | 2.4221: Install compressor air intakes in coolest locations | $330 | $300 |
$330
13
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,343 | $1,000 |
$1,343
52
kWh
|
- | - | - | |
06 | 2.7231: Use radiant heater for spot heating | $3,422 | $10,592 | - |
$3,422
-
MMBtu
|
- | - | |
07 | 2.4314: Use synthetic lubricant | $72 | $100 |
$72
3
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $8,800 | $20,107 |
$5,185
200
kWh
|
$3,422
-
MMBtu
|
$81 | $112 | ||
TOTAL IMPLEMENTED | $8,387 | $19,382 |
$4,772
184
kWh
|
$3,422
-
MMBtu
|
$81 | $112 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs