| Assessment Year | 2007 |
|---|---|
| Principal Product | Water Based Colorants |
| NAICS | 325510: Paint and Coating Manufacturing |
| SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
| Sales Range | $10 M to 50M |
| # of Employees | 96 |
| Plant Area |
350,000
ft2
|
| Annual Production | 35,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $300,437 | 4,073,254 |
kWh
|
$0.074 |
| Natural Gas | $153,993 | 18,041 |
MMBtu
|
$8.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $133,096 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,450 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $43,434 | $19,814 |
$43,433
2,007
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $4,359 | $2,026 |
$4,358
1,909
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $524 | $65 |
$523
24
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $11,450 | $4,951 |
$11,447
529
kWh
|
$1
-
kW-mo/yr
|
- | $1 | $1 | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,820 | $301 |
$1,819
84
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $321 | $2 |
$16
1
kWh
|
$1
-
kW-mo/yr
|
$304
-
MMBtu
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $841 | $2 |
$840
39
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,672 | $7,701 |
$2,671
124
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.4133: Use most efficient type of electric motors | $4,486 | $26,401 |
$4,485
207
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 10 | : | $9,311 | $301 |
$9,310
169
kWh
|
$1
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $53,878 | $20,001 | - | - |
$53,878
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $133,096 | $81,565 |
$78,902
5,093
kWh
|
$10
-
kW-mo/yr
|
$54,182
-
MMBtu
|
$1 | $1 | ||
| TOTAL IMPLEMENTED | $11,450 | $4,951 |
$11,447
529
kWh
|
$1
-
kW-mo/yr
|
- | $1 | $1 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs