Assessment Year | 2000 |
---|---|
Principal Product | Oil and Grease Shaft Seals |
NAICS |
n/a
|
SIC | 3053: Gaskets, Packing, and Sealing Devices |
Sales Range | $10 M to 50M |
# of Employees | 280 |
Plant Area |
60,000
ft2
|
Annual Production | 65,000,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $289,872 | 9,665,299 |
kWh
|
$0.030 |
Electricity Demand | $179,549 | 19,956 |
kW-mo/yr
|
$9.00 |
Electricity Fees | $23,430 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $124,851 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,045 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,045 | $12,005 |
$3,863
128,957
kWh
|
$2,182
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $535 | $432 |
$535
17,878
kWh
|
- | - | - | - | - | - | - | - | |
03 | 2.2515: Use optimum thickness insulation | $494 | $275 |
$494
16,413
kWh
|
- | - | - | - | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,267 | $42,720 |
$18,516
617,526
kWh
|
$9,711
-
kW-mo/yr
|
$(-14,960.0)
-
MMBtu
|
- | - | - | - | - | - | |
05 | 3.8142: Distill contaminated solvents for reuse | $19,293 | $4,085 | - | - | - | - |
$8,364
-
gal
|
- | $(-1,462.0) | $12,391 | - | |
06 | 3.6124: Burn waste oil for heat | $4,893 | $3,695 |
$1,428
53,048
kWh
|
- | - | - |
$3,620
-
gal
|
- | $(-155.0) | - | - | |
07 | 3.6125: Sell combustible waste | $22,432 | $900 | - | - | - | - | - |
$22,432
-
lb
|
- | - | - | |
08 | 3.4111: Use closed cycle process to minimize waste water production | $51,099 | $94,300 |
$(-8,927.0)
(-297,773)
kWh
|
$(-8,505.0)
-
kW-mo/yr
|
- |
$3,263
-
Tgal
|
- | - | - | - |
$65,268
-
Tgal
|
|
09 | 4.444: Install system to collect scrap | $6,793 | $1,634 | - | - | - | - | - | - | $6,793 | - | - | |
TOTAL RECOMMENDED | $124,851 | $160,046 |
$15,909
536,049
kWh
|
$3,388
-
kW-mo/yr
|
$(-14,960.0)
-
MMBtu
|
$3,263
-
Tgal
|
$11,984
-
gal
|
$22,432
-
lb
|
$5,176 | $12,391 |
$65,268
-
Tgal
|
||
TOTAL IMPLEMENTED | $6,045 | $12,005 |
$3,863
128,957
kWh
|
$2,182
-
kW-mo/yr
|
- | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs