ITAC Assessment: DS0165
ITAC logo
ITAC Assessment: DS0165
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Oil and Grease Shaft Seals
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $10
M
to 50
M
# of Employees 280
Plant Area 60,000
ft2
Annual Production 65,000,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $289,872 9,665,299
kWh
Electricity Demand $179,549 19,956
kW-mo/yr
Electricity Fees $23,430 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $124,851 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,045

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,045 $12,005 $3,863
128,957
kWh
$2,182
-
kW-mo/yr
- - - - - - -
02 2.7135: Install occupancy sensors $535 $432 $535
17,878
kWh
- - - - - - - -
03 2.2515: Use optimum thickness insulation $494 $275 $494
16,413
kWh
- - - - - - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $13,267 $42,720 $18,516
617,526
kWh
$9,711
-
kW-mo/yr
$(-14,960.0)
-
MMBtu
- - - - - -
05 3.8142: Distill contaminated solvents for reuse $19,293 $4,085 - - - - $8,364
-
gal
- $(-1,462.0) $12,391 -
06 3.6124: Burn waste oil for heat $4,893 $3,695 $1,428
53,048
kWh
- - - $3,620
-
gal
- $(-155.0) - -
07 3.6125: Sell combustible waste $22,432 $900 - - - - - $22,432
-
lb
- - -
08 3.4111: Use closed cycle process to minimize waste water production $51,099 $94,300 $(-8,927.0)
(-297,773)
kWh
$(-8,505.0)
-
kW-mo/yr
- $3,263
-
Tgal
- - - - $65,268
-
Tgal
09 4.444: Install system to collect scrap $6,793 $1,634 - - - - - - $6,793 - -
TOTAL RECOMMENDED $124,851 $160,046 $15,909
536,049
kWh
$3,388
-
kW-mo/yr
$(-14,960.0)
-
MMBtu
$3,263
-
Tgal
$11,984
-
gal
$22,432
-
lb
$5,176 $12,391 $65,268
-
Tgal
TOTAL IMPLEMENTED $6,045 $12,005 $3,863
128,957
kWh
$2,182
-
kW-mo/yr
- - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs