| Assessment Year | 2006 |
|---|---|
| Principal Product | Library Bound Books |
| NAICS | 323120: Support Activities for Printing |
| SIC | 2789: Bookbinding and Related Work |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
110,000
ft2
|
| Annual Production | 2,500,000
units
|
| Production Hrs. Annual | 4,125
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $83,487 | 1,496,186 |
kWh
|
$0.056 |
| Electricity Demand | $35,014 | 4,595 |
kW-mo/yr
|
$7.62 |
| Natural Gas | $9,258 | 762 |
MMBtu
|
$12.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,272 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,077 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.447: Automate payroll system | $15,000 | $10,500 | - | - | - | - | $15,000 | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $10,326 | $1,140 |
$6,835
122,501
kWh
|
$2,713
-
kW-mo/yr
|
- | $123 | - | $655 | |
| 03 | 2.7135: Install occupancy sensors | $304 | $675 |
$193
3,454
kWh
|
$111
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $6,945 | $1,200 | - | - |
$6,945
-
MMBtu
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,077 | $1,077 |
$689
12,343
kWh
|
$388
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $301 | $600 |
$195
3,492
kWh
|
$106
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $319 | $480 | - | - |
$319
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $34,272 | $15,672 |
$7,912
141,790
kWh
|
$3,318
-
kW-mo/yr
|
$7,264
-
MMBtu
|
$123 | $15,000 | $655 | ||
| TOTAL IMPLEMENTED | $1,077 | $1,077 |
$689
12,343
kWh
|
$388
-
kW-mo/yr
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs