Assessment Year | 2006 |
---|---|
Principal Product | Plastic |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2754: Commercial Printing, Gravure |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
450,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,316,174 | 31,307,563 |
kWh
|
$0.042 |
Electricity Demand | $736,772 | 53,671 |
kW-mo/yr
|
$13.73 |
Natural Gas | $309,703 | 29,577 |
MMBtu
|
$10.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $390,407 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $224,642 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $180,015 | $152 | - | - |
$180,015
-
MMBtu
|
|
02 | 2.2437: Recover waste heat from equipment | $12,962 | $5,000 | - | - |
$12,962
-
MMBtu
|
|
03 | 2.3113: Make ice during off peak hours for cooling | $162,249 | $310,000 | - |
$162,249
-
kW-mo/yr
|
- | |
04 | 2.3132: Recharge batteries on during off-peak demand periods | $13,938 | - | - |
$13,938
-
kW-mo/yr
|
- | |
05 | 2.1222: Install turbulators | $2,094 | $1,500 | - | - |
$2,094
-
MMBtu
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,516 | - |
$1,649
99,332
kWh
|
$1,867
-
kW-mo/yr
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,780 | $800 |
$834
50,181
kWh
|
$946
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,038 | $10,039 |
$4,706
283,517
kWh
|
$5,332
-
kW-mo/yr
|
- | |
09 | 2.7135: Install occupancy sensors | $3,815 | $1,275 |
$1,801
108,529
kWh
|
$2,014
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $390,407 | $328,766 |
$8,990
541,559
kWh
|
$186,346
-
kW-mo/yr
|
$195,071
-
MMBtu
|
||
TOTAL IMPLEMENTED | $224,642 | $18,766 |
$7,341
442,227
kWh
|
$22,230
-
kW-mo/yr
|
$195,071
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs