ITAC Assessment: BD0299
ITAC logo
ITAC Assessment: BD0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Scrap Metal, Wood, and Paper Recycling
NAICS 331314: Secondary Smelting and Alloying of Aluminum
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 59
Plant Area 60,000
ft2
Annual Production 100,000
ton
Production Hrs. Annual 2,730
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,474 468,731
kWh
Electricity Demand $1,134 3,196
kW-mo/yr
Natural Gas $25,295 2,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,225 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,732 $3,640 $2,639
39,312
kWh
$60
-
kW-mo/yr
- $7 $26
02 2.7231: Use radiant heater for spot heating $1,386 $3,200 $73
1,220
kWh
$1
-
kW-mo/yr
$1,312
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $483 $105 - - $483
-
MMBtu
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $485 $143 $282
4,204
kWh
$6
-
kW-mo/yr
- $40 $157
05 2.7135: Install occupancy sensors $482 $220 $468
6,974
kWh
$14
-
kW-mo/yr
- - -
06 2.2515: Use optimum thickness insulation $432 $210 - - $432
-
MMBtu
- -
07 2.4221: Install compressor air intakes in coolest locations $225 $60 $220
3,275
kWh
$5
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $6,225 $7,578 $3,682
54,985
kWh
$86
-
kW-mo/yr
$2,227
-
MMBtu
$47 $183
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs