Assessment Year | 2005 |
---|---|
Principal Product | Basement Windows |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $1 M to 5M |
# of Employees | 18 |
Plant Area |
32,000
ft2
|
Annual Production | 94,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $11,570 | 266,388 |
kWh
|
$0.043 |
Electricity Demand | $5,538 | 2,556 |
kW-mo/yr
|
$2.17 |
Electricity Fees | $22,176 | - |
|
- |
Natural Gas | $22,529 | 2,484 |
MMBtu
|
$9.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,419 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,476 | $1,014 | - | - |
$1,476
-
MMBtu
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $988 | $140 |
$825
19,014
kWh
|
$163
-
kW-mo/yr
|
- | - | - | - | |
03 | 4.821: Pay bills on time to avoid late fees | $902 | - | - | - | - | - | $902 | - | |
04 | 2.7444: Close holes and openings in building such as broken windows | $436 | $1,200 | - | - |
$436
-
MMBtu
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $350 | $350 |
$173
3,995
kWh
|
$12
-
kW-mo/yr
|
- | $69 | - | $96 | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $202 | $370 | - | - |
$202
-
MMBtu
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $169 | $300 |
$146
3,365
kWh
|
$23
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $4,523 | $3,374 |
$1,144
26,374
kWh
|
$198
-
kW-mo/yr
|
$2,114
-
MMBtu
|
$69 | $902 | $96 | ||
TOTAL IMPLEMENTED | $3,419 | $3,004 |
$1,144
26,374
kWh
|
$198
-
kW-mo/yr
|
$1,912
-
MMBtu
|
$69 | - | $96 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs