Assessment Year | 2005 |
---|---|
Principal Product | Steel Doors and Frames |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
130,000
ft2
|
Annual Production | 75,000
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,690 | 906,228 |
kWh
|
$0.040 |
Electricity Demand | $5,556 | 7,553 |
kW-mo/yr
|
$0.74 |
Electricity Fees | $35,042 | - |
|
- |
Natural Gas | $115,697 | 15,932 |
MMBtu
|
$7.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $145,272 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $127,209 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $18,063 | $50,400 | - | - |
$18,063
-
MMBtu
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,422 | $1,200 |
$10,313
254,663
kWh
|
$1,109
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,740 | $2,500 | - | - |
$7,740
-
MMBtu
|
- | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $2,600 | $600 | - | - |
$2,600
-
MMBtu
|
- | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,324 | $6,150 |
$1,228
30,319
kWh
|
$96
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $823 | $2,975 |
$486
12,000
kWh
|
$17
-
kW-mo/yr
|
- | $125 | - | $195 | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $812 | $1,625 |
$355
8,789
kWh
|
$33
-
kW-mo/yr
|
- | $231 | - | $193 | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $688 | - |
$646
15,953
kWh
|
$42
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $455 | $600 |
$427
10,552
kWh
|
$28
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.7135: Install occupancy sensors | $422 | $600 |
$381
9,395
kWh
|
$41
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $235 | $140 |
$219
5,401
kWh
|
$16
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 3.4115: Recover and reuse cooling water | $42,543 | $36,180 | - | - | - | - | - | - |
$42,543
-
Tgal
|
|
13 | 4.131: Modify process to reduce material use/cost | $58,145 | $9,400 | - | - | - | - | $57,065 | $1,080 | - | |
TOTAL RECOMMENDED | $145,272 | $112,370 |
$14,055
347,072
kWh
|
$1,382
-
kW-mo/yr
|
$28,403
-
MMBtu
|
$356 | $57,065 | $1,468 |
$42,543
-
Tgal
|
||
TOTAL IMPLEMENTED | $127,209 | $61,970 |
$14,055
347,072
kWh
|
$1,382
-
kW-mo/yr
|
$10,340
-
MMBtu
|
$356 | $57,065 | $1,468 |
$42,543
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs