| Assessment Year | 1996 |
|---|---|
| Principal Product | reconditioned drums |
| NAICS |
n/a
|
| SIC | 3412: Metal Shipping Barrels, Drums, Kegs, and Pails |
| Sales Range | $5 M to 10M |
| # of Employees | 175 |
| Plant Area |
68,000
ft2
|
| Annual Production | 750,000
pieces
|
| Production Hrs. Annual | 3,200
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $78,321 | 3,782,239 |
kWh
|
$0.021 |
| Electricity Demand | $87,047 | 7,188 |
kW-mo/yr
|
$12.11 |
| Natural Gas | $247,800 | 70,793 |
MMBtu
|
$3.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $77,251 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $72,816 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4111: Use closed cycle process to minimize waste water production | $6,379 | $1,500 | - | - |
$5,426
-
Tgal
|
- | - |
$953
-
Tgal
|
|
| 02 | 2.2437: Recover waste heat from equipment | $54,934 | $80,000 |
$34,008
414,127
kWh
|
$20,926
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $5,121 | $500 |
$1,896
60,082
kWh
|
$2,725
-
kW-mo/yr
|
- | - | $500 | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,825 | $5,650 |
$602
19,050
kWh
|
$1,203
-
kW-mo/yr
|
- | $20 | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,610 | $1,160 |
$548
17,292
kWh
|
$421
-
kW-mo/yr
|
- | $1,641 | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,382 | $16,530 |
$3,539
111,958
kWh
|
$2,843
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $77,251 | $105,340 |
$40,593
622,509
kWh
|
$28,118
-
kW-mo/yr
|
$5,426
-
Tgal
|
$1,661 | $500 |
$953
-
Tgal
|
||
| TOTAL IMPLEMENTED | $72,816 | $98,530 |
$39,443
586,167
kWh
|
$26,494
-
kW-mo/yr
|
$5,426
-
Tgal
|
- | $500 |
$953
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs