| Assessment Year | 2005 |
|---|---|
| Principal Product | Edible Oils |
| NAICS | 311225: Fats and Oils Refining and Blending |
| SIC | 2079: Shortening, Table Oils, Margarine, and Other Edible Fats and Oils, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
425,000
ft2
|
| Annual Production | 1,000,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,587,378 | 31,706,661 |
kWh
|
$0.050 |
| Natural Gas | $3,252,059 | 630,497 |
MMBtu
|
$5.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $2,658,201 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,526,328 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $140,820 | $28,500 |
$140,820
2,810,785
kWh
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $94,025 | $122,830 |
$94,025
1,876,591
kWh
|
- | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $40,515 | $5,400 |
$40,515
808,686
kWh
|
- | - | - | |
| 04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $18,974 | $14,000 | - |
$18,974
-
MMBtu
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $9,987 | $2,625 |
$9,987
118,177
kWh
|
- | - | - | |
| 06 | 2.1222: Install turbulators | $8,810 | $12,000 | - |
$8,810
-
MMBtu
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,152 | $1,200 |
$7,152
142,757
kWh
|
- | - | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,506 | - |
$2,506
50,011
kWh
|
- | - | - | |
| 09 | 2.7111: Reduce illumination to minimum necessary levels | $2,512 | $400 |
$2,512
34,261
kWh
|
- | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $472 | $596 |
$472
6,658
kWh
|
- | - | - | |
| 11 | 2.4221: Install compressor air intakes in coolest locations | $464 | $350 |
$464
9,263
kWh
|
- | - | - | |
| 12 | 3.3131: Use evaporation to concentrate material | $88,374 | $20,512 | - | - |
$88,374
-
Tgal
|
- | |
| 13 | 4.114: Add/modify equipment to improve drying process | $2,243,590 | $504,283 | - | - | - | $2,243,590 | |
| TOTAL RECOMMENDED | $2,658,201 | $712,696 |
$298,453
5,857,189
kWh
|
$27,784
-
MMBtu
|
$88,374
-
Tgal
|
$2,243,590 | ||
| TOTAL IMPLEMENTED | $2,526,328 | $685,788 |
$254,954
5,007,584
kWh
|
$27,784
-
MMBtu
|
- | $2,243,590 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs