Assessment Year | 2004 |
---|---|
Principal Product | Rolled Sheet Steel Strips |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 25 |
Plant Area |
76,400
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,465 | 1,251,508 |
kWh
|
$0.056 |
Electricity Fees | $13,967 | - |
|
- |
Natural Gas | $28,700 | 4,830 |
MMBtu
|
$5.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,661 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,109 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $4,205 | $16,000 | - |
$4,205
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $3,770 | $3,597 |
$3,770
66,960
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $1,527 | $525 |
$1,527
27,110
kWh
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $1,148 | $2,000 |
$(-117.0)
(-2,080)
kWh
|
$1,265
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $552 | $450 |
$552
9,804
kWh
|
- | - | |
06 | 3.4115: Recover and reuse cooling water | $1,459 | $5,000 | - | - |
$1,459
-
Tgal
|
|
TOTAL RECOMMENDED | $12,661 | $27,572 |
$5,732
101,794
kWh
|
$5,470
-
MMBtu
|
$1,459
-
Tgal
|
||
TOTAL IMPLEMENTED | $12,109 | $27,122 |
$5,180
91,990
kWh
|
$5,470
-
MMBtu
|
$1,459
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs