Assessment Year | 2004 |
---|---|
Principal Product | Replacement Form Coils for Rotating Electrical Apparatus |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $1 M to 5M |
# of Employees | 43 |
Plant Area |
64,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,117 | 539,904 |
kWh
|
$0.056 |
Electricity Demand | $17,710 | 2,127 |
kW-mo/yr
|
$8.33 |
Natural Gas | $19,643 | 3,272 |
MMBtu
|
$6.00 |
LPG | $29,430 | 2,638 |
MMBtu
|
$11.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,039 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,996 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,390 | $1,400 |
$4,188
75,063
kWh
|
$3,202
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,675 | $2,008 |
$2,567
45,995
kWh
|
$1,963
-
kW-mo/yr
|
- | $46 | $99 | - | |
03 | 2.7231: Use radiant heater for spot heating | $2,870 | $4,800 |
$500
8,938
kWh
|
$160
-
kW-mo/yr
|
$2,210
-
MMBtu
|
- | - | - | |
04 | 2.2437: Recover waste heat from equipment | $1,514 | $1,200 | - | - |
$1,514
-
MMBtu
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,482 | - |
$840
15,054
kWh
|
$642
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,301 | $800 |
$735
13,173
kWh
|
$566
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.6214: Shut off pilots in standby equipment | $736 | - | - | - |
$736
-
MMBtu
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $426 | $297 |
$241
4,315
kWh
|
$50
-
kW-mo/yr
|
- | $65 | $70 | - | |
09 | 2.7135: Install occupancy sensors | $395 | $525 |
$202
3,638
kWh
|
$193
-
kW-mo/yr
|
- | - | - | - | |
10 | 4.447: Automate payroll system | $4,368 | $2,500 | - | - | - | $4,368 | - | - | |
11 | 4.632: Change operating conditions | $1,882 | - | - | - | - | - | - | $1,882 | |
TOTAL RECOMMENDED | $27,039 | $13,530 |
$9,273
166,176
kWh
|
$6,776
-
kW-mo/yr
|
$4,460
-
MMBtu
|
$4,479 | $169 | $1,882 | ||
TOTAL IMPLEMENTED | $17,996 | $9,022 |
$6,706
120,181
kWh
|
$4,813
-
kW-mo/yr
|
$4,460
-
MMBtu
|
$65 | $70 | $1,882 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs