| Assessment Year | 1997 |
|---|---|
| Principal Product | Corrugated Containers |
| NAICS |
n/a
|
| SIC | 2655: Fiber Cans, Tubes, Drums, and Similar Products |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
160,000
ft2
|
| Annual Production | 850,000
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $205,518 | 5,403,869 |
kWh
|
$0.038 |
| Electricity Demand | $94,194 | 11,606 |
kW-mo/yr
|
$8.12 |
| Natural Gas | $204,758 | 47,507 |
MMBtu
|
$4.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $339,962 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $331,042 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,451 | $11,496 |
$4,126
109,027
kWh
|
$1,325
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,786 | $4,140 |
$3,702
97,304
kWh
|
$1,084
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7145: Install skylights | $2,447 | $3,900 |
$2,447
64,478
kWh
|
- | - | - | - | |
| 04 | 2.7132: Install timers on light switches in little used areas | $2,305 | $1,300 |
$2,305
60,668
kWh
|
- | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $427 | $3,891 |
$297
7,913
kWh
|
$130
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,774 | $2,000 |
$3,774
68,581
kWh
|
- | - | - | - | |
| 07 | 2.2135: Repair and eliminate steam leaks | $1,629 | $875 | - | - |
$1,629
-
MMBtu
|
- | - | |
| 08 | 2.4239: Eliminate or reduce compressed air usage | $12,422 | $400 |
$12,422
225,674
kWh
|
- | - | - | - | |
| 09 | 3.5316: Contract a wood pallet recycling company | $1,500 | - | - | - | - |
$1,500
-
lb
|
- | |
| 10 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,687 | $2,500 | - | - | - | - | $1,687 | |
| 11 | 4.111: Add equipment/ operators to reduce production bottleneck | $303,534 | $400,000 | - | - | - | - | $303,534 | |
| TOTAL RECOMMENDED | $339,962 | $430,502 |
$29,073
633,645
kWh
|
$2,539
-
kW-mo/yr
|
$1,629
-
MMBtu
|
$1,500
-
lb
|
$305,221 | ||
| TOTAL IMPLEMENTED | $331,042 | $419,962 |
$22,924
471,863
kWh
|
$1,455
-
kW-mo/yr
|
$1,629
-
MMBtu
|
$1,500
-
lb
|
$303,534 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs