ITAC Assessment: BD0265
ITAC logo
ITAC Assessment: BD0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Metal Industrial Fasteners for Automotive Industry
NAICS 332722: Bolt, Nut, Screw, Rivet, and Washer Manufacturing
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 186
Plant Area 116,000
ft2
Annual Production 17,000,000
lb
Production Hrs. Annual 5,460
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $227,048 7,993,537
kWh
Electricity Demand $78,492 18,882
kW-mo/yr
Natural Gas $128,353 26,251
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,300 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7231: Use radiant heater for spot heating $27,949 $4,200 - - $27,949
-
MMBtu
- - - -
02 2.2531: Re-size charging openings or add movable cover or door $3,335 $20,000 - - $3,335
-
MMBtu
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,398 $2,861 $4,101
141,902
kWh
$1,297
-
kW-mo/yr
- - - - -
04 2.4314: Use synthetic lubricant $4,332 $1,650 $3,291
113,886
kWh
$1,041
-
kW-mo/yr
- - - - -
05 2.4221: Install compressor air intakes in coolest locations $2,701 $1,200 $2,052
70,988
kWh
$649
-
kW-mo/yr
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,323 - $1,764
61,044
kWh
$559
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,397 $2,200 $728
25,182
kWh
$230
-
kW-mo/yr
- - - $164 $275
08 2.7142: Utilize higher efficiency lamps and/or ballasts $782 $602 $289
9,959
kWh
$57
-
kW-mo/yr
- - - $258 $178
09 2.7142: Utilize higher efficiency lamps and/or ballasts $660 $424 $173
5,972
kWh
$104
-
kW-mo/yr
- - - $124 $259
10 2.7135: Install occupancy sensors $393 $330 $274
9,469
kWh
$119
-
kW-mo/yr
- - - - -
11 3.3131: Use evaporation to concentrate material $13,608 $10,512 - - - $13,608
-
Tgal
- - -
12 3.4111: Use closed cycle process to minimize waste water production $307 - - - - $43
-
Tgal
$264
-
lb
- -
13 2.3137: Use power during off-peak periods $115 - - $115
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $63,300 $43,979 $12,672
438,402
kWh
$4,171
-
kW-mo/yr
$31,284
-
MMBtu
$13,651
-
Tgal
$264
-
lb
$546 $712
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs