Assessment Year | 2012 |
---|---|
Principal Product | Embroidered textile |
NAICS | 314999: All Other Miscellaneous Textile Product Mills |
SIC | 2395: Pleating, Decorative and Novelty Stitching, and Tucking for the Trade |
Sales Range | $5 M to 10M |
# of Employees | 150 |
Plant Area |
45,000
ft2
|
Annual Production | 8,488,898
pieces
|
Production Hrs. Annual | 4,810
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,633 | 586,385 |
kWh
|
$0.059 |
Electricity Demand | $18,459 | 2,005 |
kW-mo/yr
|
$9.21 |
Electricity Fees | $9,438 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,155 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,674 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $7,941 | $50,000 |
$4,042
53,893
kWh
|
$3,899
-
kW-mo/yr
|
|
02 | 2.7221: Lower temperature during the winter season and vice-versa | $4,740 | $2,600 |
$3,626
48,341
kWh
|
$1,114
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $986 | $1,320 |
$756
10,080
kWh
|
$230
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $976 | $1,505 |
$746
9,933
kWh
|
$230
-
kW-mo/yr
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $948 | $1,058 |
$726
9,681
kWh
|
$222
-
kW-mo/yr
|
|
06 | 2.4239: Eliminate or reduce compressed air usage | $564 | $1,860 |
$435
5,805
kWh
|
$129
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $16,155 | $58,343 |
$10,331
137,733
kWh
|
$5,824
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $6,674 | $4,978 |
$5,108
68,102
kWh
|
$1,566
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs