ITAC Assessment: BD0254
ITAC logo
ITAC Assessment: BD0254
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Wheels, Bearings & Ball Transfers for Conveyors
NAICS 333613: Mechanical Power Transmission Equipment Manufacturing
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 84,000
ft2
Annual Production 20,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $239,986 4,786,269
kWh
Electricity Demand $48,032 11,495
kW-mo/yr
Natural Gas $353,642 66,858
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,595 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,861

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,778 $6,000 $6,763
184,279
kWh
$1,481
-
kW-mo/yr
- - $268 $266 -
02 2.4234: Cool compressor air intake with heat exchanger $6,110 $38,400 - - $6,110
-
MMBtu
- - - -
03 2.7111: Reduce illumination to minimum necessary levels $4,567 $521 $2,711
73,846
kWh
$1,586
-
kW-mo/yr
- - $114 $156 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,675 $700 $2,219
60,480
kWh
$1,456
-
kW-mo/yr
- - - - -
05 2.4133: Use most efficient type of electric motors $2,728 $2,885 $2,188
59,603
kWh
$540
-
kW-mo/yr
- - - - -
06 2.4314: Use synthetic lubricant $2,104 $700 $1,426
38,860
kWh
$678
-
kW-mo/yr
- - - - -
07 2.4221: Install compressor air intakes in coolest locations $1,257 $1,000 $1,257
34,260
kWh
- - - - - -
08 2.2437: Recover waste heat from equipment $1,134 $3,500 - - $1,134
-
MMBtu
- - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $826 $1,514 $663
18,086
kWh
$163
-
kW-mo/yr
- - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $766 - $462
12,577
kWh
$304
-
kW-mo/yr
- - - - -
11 2.7135: Install occupancy sensors $681 $1,350 $358
9,745
kWh
$247
-
kW-mo/yr
- - $7 $69 -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $589 $1,023 $265
7,221
kWh
$170
-
kW-mo/yr
- - $66 $88 -
13 3.5316: Contract a wood pallet recycling company $2,580 $240 - - - $2,580
-
lb
- - -
14 4.322: Eliminate old stock and modify inventory control $3,800 $2,000 - - - - - - $3,800
TOTAL RECOMMENDED $39,595 $59,833 $18,312
498,957
kWh
$6,625
-
kW-mo/yr
$7,244
-
MMBtu
$2,580
-
lb
$455 $579 $3,800
TOTAL IMPLEMENTED $24,861 $12,661 $14,838
404,302
kWh
$5,505
-
kW-mo/yr
$1,134
-
MMBtu
$2,580
-
lb
$382 $422 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs