ITAC Assessment: BD0239
ITAC logo
ITAC Assessment: BD0239
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Soft Buns and Rolls
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 97,000
ft2
Annual Production 420,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $250,715 6,266,016
kWh
Electricity Demand $111,955 12,785
kW-mo/yr
Electricity Fees $6,618 -
Natural Gas $527,015 91,742
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $330,236 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $106,777

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.4323: Use optimum size and capacity equipment $209,343 $52,500 $362,670
6,266,002
kWh
- $(-210,349.0)
-
MMBtu
- $57,022 - - -
02 2.6124: Establish equipment maintenance schedule $14,284 $500 $7,055
115,956
kWh
$18,956
-
kW-mo/yr
$(-11,727.0)
-
MMBtu
- - - - -
03 2.4239: Eliminate or reduce compressed air usage $9,587 $1,000 $7,097
177,413
kWh
$2,490
-
kW-mo/yr
- - - - - -
04 2.7145: Install skylights $6,436 $3,500 $1,980
49,511
kWh
$2,085
-
kW-mo/yr
- - $948 - $1,423 -
05 2.1133: Adjust burners for efficient operation $5,974 $2,300 - - $5,974
-
MMBtu
- - - - -
06 2.1213: Direct warmest air to combustion intake $3,041 $2,000 $(-125.0)
(-3,120)
kWh
$(-53.0)
-
kW-mo/yr
$3,219
-
MMBtu
- - - - -
07 2.4133: Use most efficient type of electric motors $2,876 $4,580 $2,277
56,869
kWh
$599
-
kW-mo/yr
- - - - - -
08 2.4221: Install compressor air intakes in coolest locations $2,532 $2,000 $1,874
46,860
kWh
$658
-
kW-mo/yr
- - - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,133 $4,850 $731
18,282
kWh
$257
-
kW-mo/yr
- - $(-522.0) - $1,667 -
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,591 - - $1,591
-
kW-mo/yr
- - - - - -
11 2.7135: Install occupancy sensors $1,457 $675 $949
23,720
kWh
$508
-
kW-mo/yr
- - - - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $704 $1,290 $584
14,602
kWh
$120
-
kW-mo/yr
- - - - - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $311 $318 $133
3,329
kWh
$40
-
kW-mo/yr
- - $58 - $80 -
14 3.5315: Lease / purchase baler; sell cardboard to recycler $3,140 $1,000 - - - $3,140
-
lb
- - - -
15 4.632: Change operating conditions $63,779 $10,000 - - $37,203
-
MMBtu
- - $26,576 - -
16 4.821: Pay bills on time to avoid late fees $1,048 - - - - - - - - $1,048
17 4.131: Modify process to reduce material use/cost $2,000 $500 - - - - - - - $2,000
TOTAL RECOMMENDED $330,236 $87,013 $385,225
6,769,424
kWh
$27,251
-
kW-mo/yr
$(-175,680.0)
-
MMBtu
$3,140
-
lb
$57,506 $26,576 $3,170 $3,048
TOTAL IMPLEMENTED $106,777 $28,513 $20,700
457,031
kWh
$23,628
-
kW-mo/yr
$31,450
-
MMBtu
$3,140
-
lb
$(-464.0) $26,576 $1,747 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs