ITAC Assessment: BD0231
ITAC logo
ITAC Assessment: BD0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Oil and Gas Filters
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 89
Plant Area 61,500
ft2
Annual Production 2,300,000
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $107,410 1,666,392
kWh
Electricity Demand $16,735 6,068
kW-mo/yr
Electricity Fees $1,972 -
Natural Gas $47,889 8,222
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $79,290

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $20,138 $57,000 $26,866
416,520
kWh
$5,304
-
kW-mo/yr
$(-12,032.0)
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,777 $1,600 $2,255
34,984
kWh
$522
-
kW-mo/yr
- - - -
03 2.7135: Install occupancy sensors $2,010 $2,025 $1,524
23,657
kWh
$486
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,061 $4,995 $978
15,168
kWh
$108
-
kW-mo/yr
- - - $(-25.0)
05 2.4221: Install compressor air intakes in coolest locations $400 $130 $320
4,956
kWh
$80
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $113 - $92
1,413
kWh
$21
-
kW-mo/yr
- - - -
07 3.2121: Convert to electrostatic powder coating $12,010 $17,500 - - - $12,010
-
gal
- -
08 4.441: Install automatic packing equipment $28,875 $15,000 - - - - $28,875 -
09 4.445: Install equipment to move product $28,875 $20,000 - - - - $28,875 -
10 4.447: Automate payroll system $6,240 $2,500 - - - - $6,240 -
11 3.5316: Contract a wood pallet recycling company $348 $1,000 - - - - - $348
TOTAL RECOMMENDED $102,847 $121,750 $32,035
496,698
kWh
$6,521
-
kW-mo/yr
$(-12,032.0)
-
MMBtu
$12,010
-
gal
$63,990 $323
TOTAL IMPLEMENTED $79,290 $56,730 $2,667
41,353
kWh
$623
-
kW-mo/yr
- $12,010
-
gal
$63,990 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs