Assessment Year | 2002 |
---|---|
Principal Product | Candle |
NAICS |
n/a
|
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
600,000
ft2
|
Annual Production | 1,900,000
pieces
|
Production Hrs. Annual | 13,440
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $338,592 | 10,425,580 |
kWh
|
$0.032 |
Electricity Demand | $281,367 | 27,578 |
kW-mo/yr
|
$10.20 |
Electricity Fees | $1,971 | - |
|
- |
Natural Gas | $247,188 | 47,945 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $316,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $103,858 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2191: Substitute hot process fluids for steam | $185,274 | $20,000 | - | - |
$185,274
-
MMBtu
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $8,898 | $12,020 |
$6,117
188,209
kWh
|
$2,781
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,835 | $2,232 |
$4,341
133,558
kWh
|
$3,494
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $6,079 | $6,000 | - | - |
$6,079
-
MMBtu
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,027 | $1,000 |
$1,678
51,630
kWh
|
$1,349
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.1222: Install turbulators | $2,272 | $3,500 | - | - |
$2,272
-
MMBtu
|
- | - | - | |
07 | 2.7135: Install occupancy sensors | $2,219 | $1,425 |
$1,141
35,116
kWh
|
$1,078
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,901 | $2,000 |
$1,053
32,397
kWh
|
$848
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2511: Insulate bare equipment | $1,141 | $1,018 | - | - |
$1,141
-
MMBtu
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $652 | - |
$361
11,121
kWh
|
$291
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10 | $200 |
$65
1,997
kWh
|
$28
-
kW-mo/yr
|
- | $(-35.0) | $(-48.0) | - | |
12 | 2.2135: Repair and eliminate steam leaks | $126 | $100 | - | - |
$126
-
MMBtu
|
- | - | - | |
13 | 4.652: Replace existing equipment with more suitable substitutes | $70,000 | $40,000 | - | - | - | - | - | $70,000 | |
14 | 4.447: Automate payroll system | $24,960 | $17,300 | - | - | - | - | - | $24,960 | |
15 | 4.821: Pay bills on time to avoid late fees | $2,004 | - | - | - | - | - | - | $2,004 | |
TOTAL RECOMMENDED | $316,398 | $106,795 |
$14,756
454,028
kWh
|
$9,869
-
kW-mo/yr
|
$194,892
-
MMBtu
|
$(-35.0) | $(-48.0) | $96,964 | ||
TOTAL IMPLEMENTED | $103,858 | $69,320 |
$6,117
188,209
kWh
|
$2,781
-
kW-mo/yr
|
- | - | - | $94,960 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs