Assessment Year | 2002 |
---|---|
Principal Product | Metal Stamping Assemblies |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
70,000
ft2
|
Annual Production | 150,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,659 | 1,179,708 |
kWh
|
$0.084 |
Electricity Fees | $1,117 | - |
|
- |
Natural Gas | $28,367 | 3,088 |
MMBtu
|
$9.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,338 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $5,734 | $6,000 | - |
$5,734
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,911 | $1,300 |
$2,911
34,457
kWh
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $1,611 | $4,440 |
$1,611
19,060
kWh
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,008 | $400 |
$1,008
11,932
kWh
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $517 | $840 |
$517
6,122
kWh
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $429 | $975 |
$429
5,070
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $212 | $175 |
$141
1,664
kWh
|
- | - | $71 | |
08 | 3.4151: Minimize water usage | $753 | $690 | - | - |
$753
-
Tgal
|
- | |
09 | 3.5316: Contract a wood pallet recycling company | $850 | $100 | - | - | - | $850 | |
10 | 4.821: Pay bills on time to avoid late fees | $313 | - | - | - | - | $313 | |
TOTAL RECOMMENDED | $14,338 | $14,920 |
$6,617
78,305
kWh
|
$5,734
-
MMBtu
|
$753
-
Tgal
|
$1,234 | ||
TOTAL IMPLEMENTED | $14,338 | $14,920 |
$6,617
78,305
kWh
|
$5,734
-
MMBtu
|
$753
-
Tgal
|
$1,234 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs