Assessment Year | 2001 |
---|---|
Principal Product | Ball and Roller Bearings |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
213,000
ft2
|
Annual Production | 50,000,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $854,857 | 18,067,488 |
kWh
|
$0.047 |
Electricity Demand | $116,666 | 34,301 |
kW-mo/yr
|
$3.40 |
Electricity Fees | $51,216 | - |
|
- |
Natural Gas | $48,169 | 11,467 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $838 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $23,060 | $28,920 | n/a |
$21,226
448,771
kWh
|
$1,834
-
kW-mo/yr
|
- | - | - |
02 | 2.2437: Recover waste heat from equipment | $15,876 | $16,455 | n/a | - | - |
$15,876
-
MMBtu
|
- | - |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,419 | $7,120 |
$4,891
103,409
kWh
|
$528
-
kW-mo/yr
|
- | - | - | |
04 | 2.7231: Use radiant heater for spot heating | $4,255 | $4,000 | - | - |
$4,255
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $3,191 | $1,200 |
$2,738
57,878
kWh
|
$453
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,345 | $1,000 |
$2,103
44,454
kWh
|
$242
-
kW-mo/yr
|
- | - | - | |
07 | 2.2437: Recover waste heat from equipment | $2,269 | $1,500 | - | - |
$2,269
-
MMBtu
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $838 | $400 |
$751
15,864
kWh
|
$87
-
kW-mo/yr
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $559 | $541 |
$283
5,992
kWh
|
$28
-
kW-mo/yr
|
- | - | $248 | |
10 | 3.3131: Use evaporation to concentrate material | $13,105 | $27,000 | n/a | - | - | - |
$13,105
-
Tgal
|
- |
TOTAL RECOMMENDED | $70,917 | $88,136 |
$31,992
676,368
kWh
|
$3,172
-
kW-mo/yr
|
$22,400
-
MMBtu
|
$13,105
-
Tgal
|
$248 | ||
TOTAL IMPLEMENTED | $838 | $400 |
$751
15,864
kWh
|
$87
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs