ITAC Assessment: BD0192
ITAC logo
ITAC Assessment: BD0192
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Structural Buildings
NAICS
n/a
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $100
M
to 500
M
# of Employees 800
Plant Area 943,653
ft2
Annual Production 110,000
units
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $455,833 15,317,823
kWh
Electricity Demand $379,352 33,293
kW-mo/yr
Electricity Fees $20,032 -
Natural Gas $648,252 120,883
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,025,188 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7231: Use radiant heater for spot heating $276,125 $40,500 $4,852
162,803
kWh
$3,471
-
kW-mo/yr
$267,802
-
MMBtu
- - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $36,965 $4,300 $22,922
769,317
kWh
$14,043
-
kW-mo/yr
- - - - - - -
03 2.7122: Disconnect ballasts $27,741 $12,400 n/a $15,703
526,931
kWh
$9,620
-
kW-mo/yr
- - - - - - $2,418
04 2.7142: Utilize higher efficiency lamps and/or ballasts $20,184 $51,960 $15,700
526,886
kWh
$4,847
-
kW-mo/yr
- - - - $(-363.0) - -
05 2.1213: Direct warmest air to combustion intake $12,605 $35,000 $(-268.0)
8,994
kWh
$(-144.0)
-
kW-mo/yr
$13,017
-
MMBtu
- - - - - -
06 2.4133: Use most efficient type of electric motors $11,555 $24,950 $7,919
265,731
kWh
$3,636
-
kW-mo/yr
- - - - - - -
07 2.4314: Use synthetic lubricant $9,075 $5,000 $5,627
188,863
kWh
$3,448
-
kW-mo/yr
- - - - - - -
08 2.1222: Install turbulators $8,641 $1,500 - - $8,641
-
MMBtu
- - - - - -
09 2.4221: Install compressor air intakes in coolest locations $6,939 $5,000 $4,303
144,413
kWh
$2,636
-
kW-mo/yr
- - - - - - -
10 2.7135: Install occupancy sensors $2,689 $2,700 $1,395
46,822
kWh
$1,294
-
kW-mo/yr
- - - - - - -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,513 $690 $925
31,054
kWh
$588
-
kW-mo/yr
- - - - - - -
12 3.2121: Convert to electrostatic powder coating $420,915 $581,000 - - - - $420,915
-
gal
- - - -
13 3.2121: Convert to electrostatic powder coating $168,710 $9,250 - - - - $168,710
-
gal
- - - -
14 3.5315: Lease / purchase baler; sell cardboard to recycler $11,512 $7,000 n/a - - - - - $11,512
-
lb
- - -
15 3.4115: Recover and reuse cooling water $4,930 $12,000 $(-468.0)
15,691
kWh
$(-229.0)
-
kW-mo/yr
- $5,627
-
Tgal
- - - - -
16 3.3131: Use evaporation to concentrate material $4,091 $3,600 - - - $4,091
-
Tgal
- - - - -
17 3.4154: Eliminate leaks in water lines and valves $598 $250 - - $306
-
MMBtu
$292
-
Tgal
- - - - -
18 3.5316: Contract a wood pallet recycling company $400 $180 - - - - - - - $400 -
TOTAL RECOMMENDED $1,025,188 $797,280 $78,610
2,687,505
kWh
$43,210
-
kW-mo/yr
$289,766
-
MMBtu
$10,010
-
Tgal
$589,625
-
gal
$11,512
-
lb
$(-363.0) $400 $2,418
TOTAL IMPLEMENTED $14,244 $27,650 $9,314
312,553
kWh
$4,930
-
kW-mo/yr
- - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs